Creating a schedule

  1. In the navigation menu, click Configuration.
  2. In the Configuration menu, expand Schedule & Holiday, and then click Schedule.
  3. In the Schedule module, click Add New.
  4. In the Name field, enter a unique name for the schedule.
  5. Optional: In the Description field, enter a description for the schedule.
  6. If your system is partitioned, in the Partition list, select a partition.
  7. Click Save.
    After you click the Save button, additional settings appear.
  8. To add a time period to the schedule, complete the following steps:
    1. On the General tab, in the Time Periods area, click Add.
    2. Select the check box for each day that you want to add to the time period.
    3. Click the Start Time field, and adjust the start time.
    4. Click the End Time field, and adjust the end time.
      The Duration (Hrs) field updates to display the schedule duration.
    Note: You can add multiple time periods to a schedule.
  9. To view the groups that the schedule is assigned to, click the Groups tab.
  10. To apply holiday groups to the schedule, click the Holiday tab, and add holiday groups to modify the schedule as required.
  11. Optional: To view a preview of the schedule's activation times, click Preview Activation Times.
  12. Click Save.
  13. Close the schedule editor.